Sr.# | Period / Contract # | Description | Client |
---|---|---|---|
16 | 01/04/1999 - 30/11/2000 Sub-Contract |
Construction Of Curb & Gutter, Side walks, Paving Tiles at Hasa | Madim Al Hajri Eng. Nabil Ayyash. |
17 | 06/03/1999 - 31/05/2000 Sub-Contract |
Site Preparation, Back filling and Asphalt Paving at Jubail | Salah Al Hanaki co. Mr. Fawsi |
18 | 10/05/1999 - 30/06/1999 Sub-Contract |
Construction Of Curb & Gutter at Al Hasa. | A.N. Al Binali & Sons Co. Mr. Elie El Hawi. |
19 | 01/12/1998 - 30/05/1999 Sub-Contract |
Construction Of Curb & Gutter, Side walk, Paving Tiles at Jubail | Jufal & Naif Obaid Al Shammari co. |
20 | 27/08/1994 - Jan. 1995 Sub-Contract |
Supply & Delivery & Laying Of Rip-Rap Stone, Site Grading, Watering & Compaction | ALTAIF, Dammam Stadium |
21 | 28/03/1994 - 19/09/1994 DASA01 - 94-M-0022 |
Asphalt Paving | U.S. ARMY, Riyadh |
22 | 20/09/1993 - 30/01/1994 DASA01-93-C-0034 |
Pave Hazardous Waste Storage Area | ARCENT, U.S. ARMY Major Clemons |
23 | 14/10/1993 - 24/11/1993 W.O.024 / 93 |
Delivery Of Concrete Pads | AL BILAD Fire Fighting System Mr.Ravindran |
24 | 10 / 08 / 93 - 05 / 09 / 93. DASA01-93-C-0025 |
General Paving at Camp Lucky Base | ARCENT, U.S. ARMY SPC Anders |
25 | 1991 | Construction of Curb & Gutter and Sidewalk | RET SER ENG. AGENCY LRR-E-1 Dharan MODA Proj. |
26 | 1991 | Construction of Curb & Gutter and Sidewalk | AL-GAID EST. Riyadh MODA Safwa Project |
27 | 1988 - 1989 | Construction of Curb & Gutter and Sidewalk | TAMIMI CO.(TAFMEC) Doha Aramco H. Project |
28 | 1986 - 1987 | Construction of Curb & Gutter and Sidewalk | REDEC DAELIM S.A. Rastanura & Dharan H/C Exp`n Project |
29 | 1986 | Construction of Curb & Gutter and Sidewalk | POONG LIM S.A. Petromin H.Project |
30 | 1985 - 1986 | Construction of Curb & Gutter and Sidewalk | NAM KWANG Dammam, 2nd Indl. Area Project |